Client ASSOCIATION GLATIGNY VERSAILLES
Architect Eric PUISEUX / LAGOUGE & ROUSSEL
Area 4836m²
Construction cost 5,230,000€
Scope of services Structure and services
Delivery date 2007
Programme - EN
Rehabilitation and extension of 4-storey building including 30 classrooms and ancillary rooms above single level basement. Within existing building, construction of homework rooms with work benches, canteen alterations and provision of additional self-service line. Compact building to maximize external space.
Particularités Techniques - EN
Built on occupied site. Difficulty to management construction on cramped site in presence of pupils. Connection to existing buildings required rehabilitation work.