Client Adoma
Architect Muriel Germak
Area 4100m²
Construction cost 9,700,000€
Scope of services Consultant engineer, building economist
Delivery date In progress
Programme - EN
Construction of 190-unit social residence and demolition of existing foyer.
Particularités Techniques - EN
Demolition required asbestos removal. Reinforced concrete structure. Thermal bridge breakers at intermediate floor/elevation connections. Roof terraces clad with zinc sheeting. Space heating and domestic hot water supplied by boilers located on ground floor. Mechanical ventilation. Provision of open air retention pond.